Data Centers Are Coming to Georgia. Is Grantville Next?
Georgia Power has signed up 12,400 megawatts of big new customers, and nine in 10 projects in its pipeline are labeled data centers. Here is what a data center needs, who decides where one goes, and how Grantville measures up. Part 1 of a six-part series.

Part 1 of a six-part series: Data Centers and Grantville.
GRANTVILLE: Come off I-85 at Exit 35 and turn onto Highway 29 South, and a dark blue billboard announces what is coming: “Class A Industrial” and “1,035,000 SF.” Power lines run along the road overhead. Since last December, Grantville’s zoning code has allowed data centers. And across Georgia, data centers are the fastest-growing thing on the power grid.
So many residents are asking the same question: is Grantville next?
This series answers that question one piece at a time, from public records. Part 1 starts with the basics: what a data center is, what it needs, how many are coming to Georgia, who decides where they go, and how Grantville measures up. Here is the short answer. Nobody has applied to build a data center in Grantville. But the city has opened the door, the mayor has said he wants one, and a power study on a 196-acre site near the interstate exists but has not been made public.
What a data center is
Grantville’s own zoning code defines it: “a facility used primarily for the storage, management, processing and dissemination of data and information.” In plain terms, it is a large, windowless building full of computer servers. The servers run websites, phone apps, streaming video, cloud storage and, more and more, artificial intelligence. They run day and night, and they make a lot of heat.
That is why the buildings matter to the places around them. A data center needs four things in large amounts:
- Power. Big campuses proposed in Coweta County have been reported at 700 to 900 megawatts, the Newnan Times-Herald reported. Power on that scale comes over high-voltage transmission lines into a dedicated substation, not off the poles on a neighborhood street.
- Water. It depends on how the servers are cooled. The U.S. Department of Energy explains that closed-loop systems use little water, while evaporative cooling towers use a lot. Coweta filings have ranged from about 28,000 gallons a day to 9.1 million gallons a day for one early version of a project.
- Land. Coweta proposals have run from about 200 to more than 800 acres, and buffers from homes shrink the usable space.
- Fiber. Long-haul internet lines, which often follow interstates.
How many are coming to Georgia
Georgia Power, the state’s largest utility, has to report its big new customers to the Georgia Public Service Commission every three months. Its report for the first quarter of 2026 shows the scale:
- 31 large customers had committed to take power, totaling 12,400 megawatts through the mid-2030s, as of March 31, 2026. Twenty-one had broken ground, and 10 were already online.
- Georgia Power’s full pipeline of large projects, including ones still at early stages, totaled 73,100 megawatts. The company’s project list labels about nine in 10 of them “Data Center/Crypto.” Names and locations are blacked out.
For a sense of size, Georgia Power currently deploys about 22,000 megawatts statewide, according to the PSC’s September 2026 data center fact sheet. On Dec. 19, 2025, the commission approved 9,985 megawatts of new power generation, about 80% of it expected to serve data centers. By August 2026, Georgia Power had signed customers for all of it, the PSC says, including a single 3,200-megawatt data center contract.
Closer to home:
- Coweta County has seen five data center proposals, the Times-Herald reported in June. Commissioners approved one, Project Sail, in a 3-2 vote in April. In June they paused new applications for 180 days, a moratorium set to end about Dec. 13. It does not apply inside Grantville’s city limits.
- Fayetteville is home to the QTS data center campus on more than 600 acres off Highway 54 West. The city council approved its development agreement unanimously in 2023, The Citizen reported. In March 2026, the city changed its code to bar any future data centers.
- Hogansville, just down I-85 in Troup County, studied a possible 600-megawatt data center on 437 acres, the Columbus Ledger-Enquirer reported in November 2025. Its city council voted 5-0 on Feb. 2, 2026, for a 90-day data center moratorium that covers that site, and extended it 4-0 on Sept. 8, the February and September minutes show.
Who decides
A data center is not one decision. It is a chain of them, and different players hold each link.
- Developers and operators. Land developers often assemble a site and win approvals, then sell or lease to the company that runs the servers. In Coweta, the Project Sail filing was made by Atlas Development, LLC, according to the state’s regional review form.
- Power companies. Georgia Power is regulated by the PSC. About 50 Georgia cities, including Grantville, run their own electric systems and buy wholesale power through MEAG Power. Grantville has been a MEAG member since 1975.
- Development authorities. These appointed boards court new industry and can own land and offer tax breaks. In Hogansville, city records showed a developer who sits on the Fayette County Development Authority board negotiating with the Hogansville Development Authority for the 437 acres, the Ledger-Enquirer reported.
- The state. Projects this large go through a Development of Regional Impact review by the Georgia Department of Community Affairs and the regional commission.
- Local councils and commissions. They control zoning. In Grantville, that means City Council, which would vote in public on any data center permit.
Is Grantville a good fit?
Mayor Richard Proctor thinks so. In June 2025 he told the Times-Herald that a “wide-open 196-acre wooded property” at the I-85 exit “would be perfect for a data center.” In May 2026 he wrote an opinion column in the Atlanta Journal-Constitution titled “It’s time for Grantville to say yes to data centers.”
Here is how the town measures up against the list, based on the record so far.
| Need | What Grantville has | What is missing or unknown |
|---|---|---|
| Land | A 196-acre wooded site near I-85 that the mayor has promoted. Zoning that has allowed data centers by special use permit since Dec. 15, 2025 | The owner and exact parcel have not been named in any report. The Ledger is checking county records |
| Power | A city electric system that buys through MEAG. The mayor said the site owner paid $25,000 for a MEAG study, which found a supply line nearby | The mayor said a substation would cost $123 million, paid by a developer or end user, the Ledger-Enquirer reported. The study has never been released |
| Water | A city water system with about 1,239 connections, according to federal drinking water records | Grantville does not make its own drinking water. It buys treated water from the Coweta County Water and Sewer Authority. No capacity letter for a data center has been found |
| Fiber and roads | I-85 at Exit 35 | No public fiber route map for Grantville |
One number shows the gap. When Grantville bought extra electricity this year, through a May deal with the City of Griffin and MEAG, the amount was 277 kilowatts. A 700-megawatt data center would need more than 2,500 times that.
Residents have their own list. “We have a strain on our water. We have a strain on our electrical,” Trista Parker, a downtown business owner, told council in December 2025, according to the meeting video. How that December vote happened, and who voted which way, will be told later in this series.
Follow every item on the Data Center Watch tracker.
Sources
- Water connections: U.S. EPA Safe Drinking Water Information System record for Grantville. MEAG membership since 1975: Grantville council work session, Apr. 13, 2026, and the city FY2025 audit. The Ledger counted the Data Center/Crypto rows in the project list attached to Georgia Power’s Q1 2026 report. No one named in this story was interviewed for it.
- Georgia Power: Large Load Economic Development Report, Q1 2026, filed with the Georgia PSC (Docket 56002)
- Georgia Public Service Commission: data center fact sheet (Sept. 2026)
- U.S. Department of Energy: cooling water efficiency opportunities for data centers
- Newnan Times-Herald: Where Coweta’s five proposed data centers stand (June 2, 2026)
- Newnan Times-Herald: Commissioners approve Project Sail data center in split 3-2 vote (Apr. 7, 2026)
- Newnan Times-Herald: Commissioners approve 180-day data center moratorium (June 17, 2026)
- Georgia DCA: Development of Regional Impact #4361 (Project Sail), initial form
- The Citizen: Fayetteville approves development agreement for 612-acre QTS data center (June 19, 2023)
- City of Fayetteville: Fact Checker (data centers)
- Columbus Ledger-Enquirer: Hogansville data center debate (Nov. 25, 2025)
- City of Hogansville: council minutes, Feb. 2, 2026
- City of Hogansville: council minutes, Sept. 8, 2026
- Newnan Times-Herald: Grantville eyes data center for key property near I-85 (June 20, 2025)
- Atlanta Journal-Constitution: opinion by Mayor Richard Proctor (May 2026)
- Columbus Ledger-Enquirer: Grantville mayor on data centers (Jan. 8, 2026)
- City of Grantville: Dec. 15, 2025 agenda packet (Ordinance 2025-17 text)
- City of Grantville: May 18, 2026 agenda packet (MEAG excess power letter)
- City of Grantville: council meeting video, Dec. 15, 2025